Drafting a Demand Letter for a Delayed Housing Project in the Philippines

Below is a comprehensive legal discussion on drafting a demand letter for a delayed housing project in the Philippines. This article covers the relevant laws and regulations, standard practices, and strategic considerations. Please note that while this discussion is intended to be informative, it is not a substitute for personalized legal advice.


1. Overview and Purpose of a Demand Letter

A demand letter is a formal notice sent to an individual or entity, stating a legal claim and specifying the remedy sought. In the context of a delayed housing project in the Philippines, a demand letter:

  • Notifies the developer of the specific delays and contractual breaches.
  • Articulates the buyer’s rights under Philippine law.
  • Sets a clear deadline for the developer to rectify or respond.
  • Provides a framework for negotiation and potential dispute resolution before resorting to litigation or other legal remedies.

Drafting a well-structured, legally supported demand letter is crucial. It demonstrates serious intent, preserves the buyer’s rights, and may serve as evidence in case of future legal proceedings.


2. Relevant Laws and Regulations

Several Philippine laws and government agencies govern real estate transactions, particularly relating to residential developments. Understanding these legal foundations will help shape the content of your demand letter.

2.1 Presidential Decree No. 957 (PD 957)

PD 957, known as the “Subdivision and Condominium Buyers’ Protective Decree,” ensures protection for buyers in real estate projects. Its implementing rules and regulations:

  • Require developers to obtain the necessary licenses and permits.
  • Mandate compliance with approved plans, project schedules, and contractual obligations.
  • Authorize the Department of Human Settlements and Urban Development (DHSUD; formerly HLURB) to regulate and monitor developers.

Under PD 957, if a developer fails to complete a project or deliver the housing unit as promised, the buyer can file a complaint and invoke the rights provided under PD 957 and its IRR.

2.2 The Maceda Law (Republic Act No. 6552)

Also known as the Realty Installment Buyer Protection Act, the Maceda Law grants certain reliefs to buyers who have paid at least two years of installments for residential real estate. Key provisions include:

  • Right to a refund of a portion of installments in case the buyer cancels the contract (certain percentages apply based on how long payments have been made).
  • Grace period for installment payments.
  • Protection from arbitrary cancellation of the purchase contract by the seller or developer.

In cases of project delays, you may invoke the Maceda Law if the situation involves the possibility of canceling the purchase and demanding a refund or other relief.

2.3 The Civil Code of the Philippines

The Civil Code provides the general legal framework for contracts and obligations in the Philippines. Crucial sections include:

  • Article 1191: A party may seek rescission (cancellation) of the contract if the other party fails to comply with obligations.
  • Articles 1159 and 1306: Stipulate that obligations arising from valid contracts have the force of law and must be complied with in good faith.
  • Article 2209: Governs interest on indemnities for damages in case of breach.

Invoking these provisions in your demand letter strengthens your position and sets a clear basis for your claims.

2.4 Consumer Act of the Philippines (RA 7394) – If Applicable

Although the Consumer Act primarily covers general consumer goods and services, some of its provisions on deceptive practices could apply if a developer engages in misleading marketing or fails to deliver as promised.


3. Key Elements of the Demand Letter

When drafting your demand letter for a delayed housing project, ensure that it contains the following key elements:

  1. Heading and Formalities

    • Your name, address, and contact details.
    • The developer’s official registered name, address, and contact details.
    • The date of writing.
  2. Salutation

    • Address the developer or the developer’s authorized representative formally (e.g., “Dear [Name of Developer or Corporate Officer]”).
  3. Statement of Facts

    • Clearly and chronologically state the pertinent details:
      • Dates of reservation, contract signing, and payment milestones.
      • The initially promised turnover date or completion date of the project.
      • Any communications regarding project updates and deadlines.
    • Attach supporting documents (receipts, contracts, official communications) if relevant.
  4. Legal Basis

    • Refer to the specific provisions of:
      • PD 957 (Subdivision and Condominium Buyers’ Protective Decree), if relevant.
      • The Maceda Law, if you have paid at least two years of installments.
      • Applicable sections of the Civil Code (e.g., Articles 1191, 2209).
      • Provisions in your Contract to Sell or Deed of Conditional Sale regarding construction timelines and developer obligations.
    • State how the developer’s delays constitute a breach of contract.
  5. Demands or Relief Sought
    Depending on your situation and preference, you may request:

    • Completion of the project by a specific date (often accompanied by a threat of legal action or cancellation if not met).
    • Delivery of the unit in acceptable condition within a specified timeframe.
    • Refund of payments already made, either partially or in full (referencing the Maceda Law for guidance, if applicable).
    • Damages or other compensation for inconvenience, rentals, or other expenses incurred due to the delay (supported by the Civil Code).
    • Interest for the period of delay, if stipulated or permissible under the contract or the law.
  6. Deadline for Compliance

    • Clearly indicate a reasonable deadline by which the developer must respond or take action (e.g., 15 calendar days or 30 calendar days from receipt of the letter).
    • If you are open to negotiation or arbitration, indicate that as well.
  7. Consequences of Non-Compliance

    • Inform the developer that failure to comply with the demand by the specified date may result in legal action.
    • State that you reserve the right to seek all available remedies, including filing a complaint with the DHSUD (formerly HLURB) or pursuing civil litigation.
  8. Closing and Signature

    • Politely but firmly restate your demand.
    • Sign above your typed name, or for corporate entities, include your official designation.

4. Practical Tips and Considerations

  1. Gather Evidence

    • Before sending the letter, compile all relevant documents: contracts, official receipts, bank statements, marketing brochures, written promises of turnover dates, and any email or text message communications.
    • Evidence ensures that your factual claims are supported.
  2. Be Clear and Concise

    • State your demands and legal arguments in plain language. Overly technical or convoluted drafting can cause confusion.
  3. Maintain Professional Tone

    • While it is important to be firm, remain courteous. Keep the language free of unnecessary threats or emotional rants.
  4. Retain Copies

    • Keep copies of everything, including proof of mailing or personal service of the letter (e.g., registered mail with return card, courier confirmation).
    • Proper documentation is critical if you need to escalate your claim.
  5. Seek Legal Advice

    • Where significant sums are involved or where the developer is uncooperative, consult with a lawyer to ensure your demand letter meets all technical requirements.

5. Possible Remedies After Sending the Demand Letter

If the developer does not comply or does not respond satisfactorily within the deadline stated in your demand letter, you have several options:

  1. Filing a Complaint with DHSUD

    • The DHSUD (formerly HLURB) is the regulatory body overseeing real estate developers.
    • Under PD 957, a buyer can file a complaint for specific performance, rescission of contract, refund, or damages.
  2. Civil Court Action

    • If negotiations fail, you can pursue a civil lawsuit for breach of contract under the Civil Code.
    • Possible remedies include court-ordered specific performance (forcing the developer to complete the project/unit), rescission (cancel the contract), and damages (monetary compensation).
  3. Arbitration or Mediation

    • If your contract includes an arbitration clause, or if both parties agree, you can proceed with arbitration or mediation, which may be faster and less adversarial than a court suit.
  4. Joint Complaints or Class Actions

    • If multiple buyers are affected by the same delay, a collective approach may be more cost-effective and exert greater pressure on the developer.
    • Consult an attorney for the viability of a class action or joint complaint under Philippine procedural rules.

6. Template Outline of a Demand Letter

Below is a sample outline for a demand letter. Adjust language and specifics to your unique situation:

[Date]

[Your Name]
[Your Address]
[Your Contact Details]

[Name of Developer/Corporate Officer]
[Developer’s Address]
[Developer’s Contact Details]

Subject: Demand Letter for Delayed Turnover of [Specify Unit Details or Project]

Dear [Name or Authorized Representative]:

I am writing to express my serious concerns regarding the delayed turnover of [Unit/Property Details] in the [Name of Development Project] located at [Address]. On [Date of Contract], I entered into a Contract to Sell (or Deed of Conditional Sale) with your company, wherein it was agreed that turnover would occur by [Original Turnover Date]. As of today, [Specify Current Date], no satisfactory completion or turnover has been made.

I. Statement of Facts
- [Brief chronology of events and payments made]
- [Previous communications or promised deadlines]

II. Legal Basis
- [Cite PD 957, Maceda Law (if applicable), Civil Code provisions, or relevant contractual clauses]
- [Explain how these laws/contractual clauses entitle you to relief]

III. Demand for Relief
Given the prolonged delay and the breach of our agreement, I hereby formally demand:
1. [Completion and turnover of the unit within X days]
2. [Alternatively, refund of all payments, inclusive of interest and other expenses, based on R.A. 6552, if applicable]
3. [Damages for the inconvenience and added costs (e.g., rental expenses, etc.), if warranted under the Civil Code]

IV. Deadline for Compliance
Please respond to this demand within [Specify Reasonable Period, e.g., 15 calendar days] from receipt of this letter. Failure to comply shall leave me no alternative but to pursue all legal remedies available under Philippine law, including filing a complaint before the Department of Human Settlements and Urban Development (DHSUD) or initiating court proceedings.

V. Conclusion
I trust that we can resolve this matter promptly. Thank you for your immediate attention.

Sincerely,

[Your Signature Above Printed Name]

7. Final Takeaways

  • A well-drafted demand letter can often prompt the developer to act, especially if they realize the buyer is knowledgeable about their legal rights.
  • Cite the relevant laws and contractual provisions, maintain a professional tone, and make specific, reasonable demands.
  • Keep precise records of all communications for use in any subsequent dispute resolution or litigation.
  • If the developer remains unresponsive or fails to comply, escalate through the DHSUD or via court action as applicable.

Disclaimer: This document is for informational purposes only and does not constitute legal advice. For a situation-specific approach, it is best to consult a qualified attorney in the Philippines.


By understanding the pertinent laws, structuring the letter properly, and setting a clear timetable for compliance, buyers can significantly increase their chances of resolving disputes over delayed housing projects without resorting to protracted legal battles.